Signalization Projects
Home Up Signalization Projects Supervisors Minutes

 

According to the latest information from our Northampton Supervisors, this page contains information on Signalization Projects underway and/or recently completed.

Location Cost (Source) Comments
1) Bristol Road and Hatboro Road (Northampton Hunt) Permit approved by PA DOT. Contract awarded 9/10/03. Construction to begin shortly and should be completed late spring or early summer of 2004.
2) Tanyard Road and Hatboro Road $60,000

(Northampton Hunt)

Permit approved by PA DOT. Contract awarded 9/10/03.  Construction underway and should be energized by March 1, 2004.
3) Bristol Road and Bustleton Pike $50,000 (Township and Northampton Crest) Engineering study completed and under review by PA DOT (coordinate Bristol Rd & Churchville Ln) with Upper Southampton. This project hasa been suspended pending budget authorization.
4) Buck Road and Rocksville Road (new) (AMOCO) $50,000 Future - to be constructed by Amoco, approved by PA DOT.
5) Lower Holland Road and Holland Road $40,000 (Township and Holland Run) Future - preliminary approval (PA DOT).
6) Buck Road and Holland Road traffic corridor (signal at Old Bristol Road to intersection of Rocksville Road) unknown Engineering study completed and under review by Board of Supervisors. Project submitted to PA DOT 12 year study.
7) Jacksonville Road and Pulinski Road $130,000 (Township) Engineering study completed and reviewed by PA DOT. Bid opening scheduled on 3/16/04.

8) Other possible signalization, projects or studies:

a) Almshouse Road and Friesland Drive

b) Tanyard Road and Friesland Drive (consider after completion of Almshouse Rd. & Friesland Dr.)

c) Second Street Pike and Worthington Mill Road

d) Second Street Pike and Sackettsford Road

e) East Holland Road and Bridgetown Pike

f) Bristol Road and Second Street Pike (modifications - coordinate with Upper Southampton)

g) Bridgetown Pike and Maple Avenue (possible modifications/changes with Lower Southampton)

h) Buck Rd & Middle Holland Rd (traffic study recommended for signal/intersection changes)

i) Bustleton Pike and Elm Avenue (traffic study recommended for consideration)

9) Completed projects:

a) Middle Holland Road and Buck Road

b) Old Bristol Road and Bridgetown Pike

c) Buck Road, Holland Road and Chinquapin Road

d) Buck Road and Old Bristol Road

e) Newtown-Richboro Road and Holland Road

f) Bristol Road and Knowles Avenue

g) East Holland Road and Buck Road

h) Second Street Pike and Tanyard Road

i) Hatboro Road and Almshouse Road

j) Second Street Pike and Crossroads Plaza

k) Buck Road and East and West Village Roads

l) Almshouse Road and Jacksonville Road

m) Bristol Road and Jacksonville Road

n) Holland Road/Upper Holland Road/Middle Holland Road corridor

o) Middle Holland Road/Jodie Road and connector road

p) Richboro Transportation Improvement Project

Second Street Pike/Almshouse Road/Newtown-Richboro Road

Newtown-Richboro Road and Township Road

q) Second Street Pike and New Road

r) Bristol Road and Davisville Road

 